Well Inspection Project
Summary
-
Objective:
- To determine the condition of the well with respect to rehabilitation and drilling of new wells.
- To determine the productivity of the wells through the use of pump test.
-
Scope:
Nine bore holes were inspected. They are as follows: Woodlands #2 & #3, Chemin Valley #1, #2 & #4, Baillies Bacolet #1, #2 & #3 and La Sagesse
- Project Duration: Project commenced in August 2013 and was completed in September 2013