Summary

  • Location: Peggy’s Whim, St Patrick
  • Objective:

    To be able to have a constant raw water supply to existing treatment plant when the primary intake is blocked.

  • Project Deliverables:

    A new concrete catchment with a holding capacity of about 600 US. gals and piping to existing raw water lines about 350ft long, to supply raw water at a rate of approximately 165 us gals per min.

  • Project Duration: Project commenced in May 2013 and was completed in November 2013.