Zulu Dam Secondary Intake
Summary
- Location: Peggy’s Whim, St Patrick
-
Objective:
To be able to have a constant raw water supply to existing treatment plant when the primary intake is blocked.
-
Project Deliverables:
A new concrete catchment with a holding capacity of about 600 US. gals and piping to existing raw water lines about 350ft long, to supply raw water at a rate of approximately 165 us gals per min.
- Project Duration: Project commenced in May 2013 and was completed in November 2013.