Munich Water Treatment Plant
Summary
-
Objective:
- To accommodate the additional demand for water with increasing population growth, thus improvement in standard
- To reduce the inconvenience caused by lack of water during periods of heavy rainfall (increase turbidity) i.e. minimizing system downtime
- To maintain adequate pressure during peak demand
- To ensure quality standards as set out by World Health Organization (WHO) and the Grenada Water Quality Act of 2005.
- To provide adequate supply for sustaining industrial and commercial development. Hence, assisting with long term planning for future water demand
-
Project Benefits:
- Employment for approximately fifteen (15) residents in the community for a duration of four (4) months
- Reduction of regular periods of water supply system downtime. Hence ,the enhancement of NAWASA relationship with the public
- To provide a multiple barrier approach towards water treatment, thus reducing the bacteriological load and improving water quality
- To provide at least one day's storage capacity
- To reduce the threat of contamination and the spread of some waterborne diseases
-
Project Description:
- Land acquisition in the amount of 8,000 sq. ft.
- Excavate and lay foundation for two (2) reinforced concrete slow sand filters, 20,000 gals. reinforced concrete clearwell and operators' quarters
- Construct filters, clearwell and operators' quarters as per design
- Construct retaining wall to provide adequate slope stabilization as deemed necessary
- Installation of 4" ø ductile iron pipes, fittings and appurtenances as network
- Installation of 4" ø bulk meter and altitude valve
- Fencing of the Water treatment compound using heavy gauge chain linked wire on metal poles with concrete bottom stabilizer
- Installation of Chlorine dosing system
- Installation of Chemical (Alum) dosing system
- Construction of Concrete Rd. approx. 300ft to site
- Provision of Electricity and lighting facilities