NAWASA Highlights Major Water Security Investments in Carriacou as G-CREWS Project Concludes

The National Water and Sewerage Authority (NAWASA) has reaffirmed its commitment to strengthening water security in Carriacou and Petite Martinique, following the official closing ceremony of the Grenada Climate-Resilient Water

NAWASA Corporate Communications

Office of the General Manager

Share

The National Water and Sewerage Authority (NAWASA) has reaffirmed its commitment to strengthening water security in Carriacou and Petite Martinique, following the official closing ceremony of the Grenada Climate-Resilient Water Sector (G-CREWS) Project, which has delivered significant investments in water storage, rainwater harvesting, healthcare infrastructure and agricultural resilience.

The investments represent an important step towards addressing longstanding water supply challenges in Carriacou, where limited freshwater resources, prolonged dry periods and extreme weather events have historically affected households, businesses and essential services.

Among the major achievements under Component Three of the project is the construction of two 100,000-imperial-gallon water storage tanks at Belair and Mt. Royal, providing a combined additional storage capacity of 200,000 imperial gallons.

The additional capacity is expected to provide approximately three to six days of water storage, strengthening NAWASA’s ability to manage supply interruptions and respond to periods of reduced water availability.

Speaking at the closing ceremony, NAWASA Board Director Valentine Douglas said the investments represent more than the completion of infrastructure works, emphasising the responsibility to ensure that the facilities continue delivering benefits to the communities they serve.

He noted that increased storage capacity provides greater operational flexibility and strengthens the Authority’s ability to maintain essential services during disruptions.

Mr. Douglas also underscored the importance of continued maintenance, monitoring and responsible management of the newly constructed facilities.

“The lasting measure of this project will be found in the service these assets provide over time,” he stated.

Acting General Manager Todd La Barrie described the investments as a significant advancement in NAWASA’s efforts to establish a more reliable and climate-resilient water supply system for Carriacou.

Reflecting on the devastation caused by Hurricane Beryl in July 2024, Mr. La Barrie recalled the vulnerability of the island’s traditional rainwater harvesting systems when roofs, storage facilities and other infrastructure were damaged.

He explained that the project was designed to strengthen the relationship between water production, storage and distribution, recognising that each component must function effectively to deliver reliable service.

The Acting General Manager also highlighted NAWASA’s ongoing efforts to extend its distribution network beyond Hillsborough and surrounding communities into southern areas of Carriacou.

He emphasised that the new storage facilities will provide operational teams with greater flexibility in managing water supply and responding to interruptions.

In addition to the two major storage tanks, the G-CREWS Project has supported improvements to communal rainwater harvesting and water storage systems at healthcare facilities.

At Mt. Royal, a communal rainwater harvesting system was retrofitted, benefiting approximately 56 households and 169 residents.

The intervention recognises the continued importance of rainwater harvesting in Carriacou, where households have traditionally depended on rainfall collection to meet their daily water needs.

Significant investments were also undertaken at healthcare facilities to strengthen their ability to maintain essential services during emergencies.

At the Princess Royal Hospital, an existing 80,000-gallon water storage tank was refurbished, while a new 100,000-gallon tank was installed.

Additional 11,400-gallon water storage systems were constructed at the L’Esterre and Windward medical stations, while protective improvements were undertaken to the water storage facility at the pharmacist’s quarters.

Minister for Health, Hon. Philip Telesford, highlighted the importance of reliable water supplies to healthcare delivery, particularly during hurricanes and other emergencies.

He reported that the interventions have added approximately 205,800 imperial gallons of resilient water storage capacity to the healthcare sector, providing an estimated five-day operational buffer.

The Minister also highlighted ongoing efforts to improve water efficiency at healthcare facilities through water audits, conservation planning and staff training.

The project’s impact extends beyond domestic water supply and healthcare to the agricultural sector.

Through the G-CREWS Challenge Fund for Agriculture, implemented by the Grenada Development Bank, farmers have received support to adopt more efficient water management and climate-resilient farming practices.

Project Development Specialist at the Grenada Development Bank, Natasha Joseph, reported that more than 300 farmers across Grenada, Carriacou and Petite Martinique have benefited from interventions under the programme.

In Carriacou, approximately 18 farmers received support for drip irrigation and micro-sprinkler systems, while 22 farmers benefited from more than 60,000 gallons of rainwater harvesting storage capacity.

The programme also includes 19 shade houses earmarked for Carriacou, with installation activities being undertaken in phases.

Ms. Joseph emphasised that the initiative was designed not only to provide equipment but also to strengthen farmers’ technical capacity through training in irrigation systems, installation and maintenance.

Head of the G-CREWS Project at the Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ), Marion Geiss, described the initiative as the result of years of collaboration among government institutions, international development partners, contractors and communities.

She highlighted the wider project’s value of approximately EC$133 million, noting that its achievements extend beyond physical infrastructure to include training, institutional strengthening, water conservation and improved approaches to freshwater management.

The G-CREWS Project has been supported by the Green Climate Fund, the Government of the Federal Republic of Germany through its International Climate Initiative, and the Government of Grenada, with GIZ providing technical implementation support.

Ms. Geiss noted that the combination of storage infrastructure, rainwater harvesting, efficient irrigation and water conservation measures provide an important foundation for addressing the growing pressures associated with climate change.

Minister for Carriacou and Petite Martinique Affairs and Local Government, Hon. Tevin Andrews, welcomed the investments, reflecting on the severe drought of 2010 when water had to be transported to Carriacou to meet the island’s needs.

He described the improvements as evidence of the progress made in strengthening the island’s capacity to withstand future water shortages.

The Minister also acknowledged the economic benefits generated through the project’s implementation, including opportunities for local contractors, equipment operators, suppliers, vendors and boat operators.

Meanwhile, NAWASA’s Planning and Development Manager, Whyme Cox, explained that although the project has reached its formal closing stage, additional operational works remain necessary before the full benefits of the new infrastructure can be realised.

These include system interconnections, pump installation and the commissioning of sections of the distribution network.

Mr. Cox encouraged residents in areas where pipelines have been extended to begin the process of applying for water service connections, noting that payment arrangements are available to assist customers.

NAWASA has expressed appreciation to the Government of Grenada, the Green Climate Fund, the Government of Germany, GIZ, the Grenada Development Bank, participating ministries, contractors, technical teams and the residents of Carriacou for their contributions and cooperation throughout the project.

The Authority has also encouraged residents to play an active role in protecting the new infrastructure, conserving water, reporting leaks and maintaining their customer accounts.

The completion of the G-CREWS Project represents an important milestone in Grenada’s efforts to strengthen climate resilience, while providing a foundation for continued investment in water production, storage and distribution.

More from News & Notices

G-CREWS Climate Resilient Water Sector Project

A major milestone was reached in Carriacou with the commissioning of G-CREWS-supported water assets, including two 100,000-imperial-gallon storage tanks at Mt. Royal and Belair. The works expand water-storage capacity on the sister isle and are intended to improve resilience during droughts, hurricanes and other climate-related disruptions. Water cisterns were also completed at the Windward Medical Station and L’Esterre Medical Centre to strengthen continuity of water supply at these health facilities.

Laura Water Treatment Plant Project Update

The Laura Water Treatment Plant had reached approximately 85% completion. Final commissioning is the next major activity.

UKCIF Southern St. George Water Supply Expansion Project

Road reinstatement remains a key part of the UKCIF works as sections affected by pipeline installation are restored.