UKCIF Southern St. George Water Supply Expansion Project

What the project involves

NAWASA is upgrading the water and wastewater network serving St. George’s and the southern corridor. The work includes improvements to the Concord Water Treatment Plant, associated transmission piping and storage, as well as the laying or upgrading of approximately 14 kilometres of water mains and 2 kilometres of sewer mains. The project will also install valves, flow meters and other equipment and will connect the Concord and Annandale supply networks so that water can be moved more reliably into Southern St. George.

The wider programme also includes improvements to wastewater infrastructure from St. George’s into Southern St. George and measures to strengthen monitoring, reduce water losses and make the water system more resilient to changing climate conditions.

Why it is needed

The project is intended to improve year-round access to potable water for customers supplied by the Annandale Water Supply System, particularly in Southern St. George. By linking Annandale with the Concord system, upgrading major mains and treatment infrastructure, and reducing losses from the network, NAWASA will have greater flexibility to move water where it is needed and strengthen the reliability of supply in the south.

The project also addresses wastewater needs in St. George’s and the southern corridor. It is a major expansion of both water and wastewater systems.

What customers can expect while it is underway

Residents, businesses and motorists in active work areas may notice excavation, temporary traffic controls, dust and changes to normal road access while pipelines are installed and roads are reinstated.

Traffic arrangements may change as work moves from one section to another.

PROJECT FACTS

Status

In progress

Parish

St George, St John

Communities served

Southern St George

Start date

April 2024

Expected completion

October 2026

Funding source

UK Caribbean Infrastructure Fund (UKCIF), funded by the UK Government through FCDO and administered by the Caribbean Development Bank

Contractor

Gilbert & Partners Engineering Company, Lot 2; CCCCI, Lot 1

Updates

10 Sep 2026

Road reinstatement remains a key part of the UKCIF works as sections affected by pipeline installation are restored.

17 Jul 2026

Road reinstatement works are continuing along Woolwich Road following water-supply expansion works in the area. Motorists and residents are asked to take care around active work zones and follow current NAWASA notices as crews move through each section.

2 Jul 2025

The Southern St. George Water Supply Expansion Project was formally launched. The programme includes the Concord water-supply works and upgrading of water and sewer infrastructure between St. George’s and the southern corridor toward Point Salines.

Gallery

Related projects

G-CREWS Climate Resilient Water Sector Project

A major milestone was reached in Carriacou with the commissioning of G-CREWS-supported water assets, including two 100,000-imperial-gallon storage tanks at Mt. Royal and Belair. The works expand water-storage capacity on the sister isle and are intended to improve resilience during droughts, hurricanes and other climate-related disruptions. Water cisterns were also completed at the Windward Medical Station and L’Esterre Medical Centre to strengthen continuity of water supply at these health facilities.

Laura Water Treatment Plant Project Update

The Laura Water Treatment Plant had reached approximately 85% completion. Final commissioning is the next major activity.