Capital works and improvement programmes underway across Grenada, Carriacou and Petite Martinique. This page is updated as projects move from planning to completion.

G-CREWS Climate Resilient Water Sector Project

A major milestone was reached in Carriacou with the commissioning of G-CREWS-supported water assets, including two 100,000-imperial-gallon storage tanks at Mt. Royal and Belair. The works expand water-storage capacity on the sister isle and are intended to improve resilience during droughts, hurricanes and other climate-related disruptions. Water cisterns were also completed at the Windward Medical Station and L’Esterre Medical Centre to strengthen continuity of water supply at these health facilities.

Laura Water Treatment Plant Project Update

The Laura Water Treatment Plant had reached approximately 85% completion. Final commissioning is the next major activity.

UKCIF Southern St. George Water Supply Expansion Project

Road reinstatement remains a key part of the UKCIF works as sections affected by pipeline installation are restored.